September 2019 → February 2020

Main Street Redevelopment Project Stage 2 Construction

Main Street Redevelopment Project Stage 2 Construction- new roundabouts and all streetscape works including paving, landscaping, street furniture, lighting
May → September 2019

Main Street Redevelopment Project Winter Shutdown

Main Street Redevelopment Project Winter Shutdown -
19 April → 26 April 2019

Main Street Redevelopment Project Easter Shutdown

Main Street Redevelopment Project Event Easter Shutdown - all construction works shutdown for the week April 19- 26 for Easter and Anzac Day public holidays
February → May 2019

Main Street Redevelopment Project Stage 1 Construction

Main Street Redevelopment Project Stage 1 Construction - underground services - stormwater, electrical
February 2019

Main Street Redevelopment Project Event

Main Street Redevelopment Project Pre-construction Event
January 2019

Main Street Redevelopment Project Tender Award

Main Street Redevelopment Project Tender Special Council Meeting to Award Tender
December 2018

Main Street Redevelopment Project Tender

Tender submissions due for Margaret River Main Street Redevelopment Project
22 February 2018

Councillor Briefing Final Design Resolution Margaret River Main Street Redevelopment Stage 2

The Shire of Augusta Margaret River invites you to attend a Council briefing on the final design resolution for Margaret River Main Street Redevelopment Stage 2. The design team will present final solutions for the Streetscape, Public Space and Traffic, Parking and Cycling.
20 April 2017

Community Meeting - Main Street Redevelopment

RSVP to amrs@amrshire.wa.gov.au or 9780 5255
21 May 2017

Feedback closes on final design