Project update 7 August 2020

Stage 2a update (Churchill Ave to Willmott Ave)
Works connecting the drainage crossovers to properties are now complete. Kerbing is being laid up the street with the footpaths following on behind.

As the footpath works progress we will work with all traders to minimise/avoid access issues whilst works are in progress.

We have made one final adjustment to the parking layout at the north entrance to town, on the east lane to facilitate access for elderly and infirm community members. No further adjustments are planned.



Stage 3 Planning
With the announcement that the State government are funding Stage 3, the Shire and BCP are working to finalise the construction plan for the final stage of the project from Fearn Avenue to Wallcliffe Road.

Whilst we are conscious of the disruption that Stage 2 works are having there will be a need for some overlap of Stage 2 and 3 construction works to ensure that we can deliver the project between now and Christmas.

We will hold an information session for local businesses in the coming weeks. Details will be available on the mainstreetmakeover.com.au website and emailed out to traders.

Stage 1a (Peanut Roundabout)
Final landscaping works are underway and will be completed next week. This will mark the completion of the northern entry to town.