Margaret River Main Street Makeover

Starting in February 2020, Margaret River’s Main Street will be transformed! The Main Street Makeover includes a range of improvements designed to create an even more enjoyable place for you to shop, eat, drink and celebrate.

You can find project updates, frequently asked questions and other up to date information on this page.

Please note this information is correct at the time of publishing. Late amendments to traffic management arrangements may be required in the case of changing site conditions. This is to facilitate ongoing project works and ensure the safety of road users and pedestrians. Please adhere to onsite

Starting in February 2020, Margaret River’s Main Street will be transformed! The Main Street Makeover includes a range of improvements designed to create an even more enjoyable place for you to shop, eat, drink and celebrate.

You can find project updates, frequently asked questions and other up to date information on this page.

Please note this information is correct at the time of publishing. Late amendments to traffic management arrangements may be required in the case of changing site conditions. This is to facilitate ongoing project works and ensure the safety of road users and pedestrians. Please adhere to onsite traffic arrangements at all times. Updated communications will be reissued as soon as practical.


  • Churchill Ave/Tunbridge St intersection closure details

    10 days ago

    Works are progressing well at the north entrance to town, with the contractor now moving south to install large pits and pipes at the Churchill Ave / Tunbridge St intersection.

    This will require the full closure of the Churchill intersection to all traffic to allow for safe construction to commence as of Friday 20 March 2020. The left turn into the Main Street via Churchill Ave will be closed.

    The Shire is looking at providing cul de sac arrangements to north and south of this intersection as soon as possible to facilitate easier access to shops near the work site....

    Works are progressing well at the north entrance to town, with the contractor now moving south to install large pits and pipes at the Churchill Ave / Tunbridge St intersection.

    This will require the full closure of the Churchill intersection to all traffic to allow for safe construction to commence as of Friday 20 March 2020. The left turn into the Main Street via Churchill Ave will be closed.

    The Shire is looking at providing cul de sac arrangements to north and south of this intersection as soon as possible to facilitate easier access to shops near the work site.

    The southern section of Bussell Hwy can be temporarily reopened to allow access to Margaret’s Forrest entrance from the North. This will also mean that businesses affected by full vehicle closure since 27 February 2020 will regain vehicle access.

    Residents and visitors are reminded that there are parking bays and access points to the Main Street behind shops south of Churchill Avenue, on Ned Higgins Lane. Refer to parking map here.

  • Parking map for visitors

    10 days ago
    Parking flyer joint pic

    The Shire has created a parking map to help visitors identify parking spots around the CBD, together with information on what the Main Street Makeover will deliver.

    Hard copies
    Accommodation providers can pick up hard copies at the Visitor Information Centre on Bussell Highway.

    Download digital copy here


    The Shire has created a parking map to help visitors identify parking spots around the CBD, together with information on what the Main Street Makeover will deliver.

    Hard copies
    Accommodation providers can pick up hard copies at the Visitor Information Centre on Bussell Highway.

    Download digital copy here


  • Progress update at the north end of town

    15 days ago
    Cemented pipes

    Work is progressing well at the north entry to town.
    Deep excavation is required to install the necessary stormwater infrastructure.
    A shutter (pictured) is being used to safeguard the trench and workers from any potential collapse.
    Stormwater pits are being are being installed along with several 1.2m diameter pipes.


    Work is progressing well at the north entry to town.
    Deep excavation is required to install the necessary stormwater infrastructure.
    A shutter (pictured) is being used to safeguard the trench and workers from any potential collapse.
    Stormwater pits are being are being installed along with several 1.2m diameter pipes.


  • Bussell Highway Road Closure from 27 February - Northern access to the town centre

    about 1 month ago

    The northern section of the Main Street (from Swings & Roundabouts Taphouse to Tunbridge St/Churchill Ave) will be closed from 27 February, with ground works commencing Friday. The closure is expected to be in place for approximately four weeks. View detour map.

    The road closure and detours are necessary to accommodate a realignment of stormwater infrastructure to avoid a conflict in utility services underground.

    Light vehicle access
    Light vehicle traffic entering from the north can access the Margaret River town site via Bussell Highway and following detours up Higgins Street and along Townview Terrace. Local traffic will still be...

    The northern section of the Main Street (from Swings & Roundabouts Taphouse to Tunbridge St/Churchill Ave) will be closed from 27 February, with ground works commencing Friday. The closure is expected to be in place for approximately four weeks. View detour map.

    The road closure and detours are necessary to accommodate a realignment of stormwater infrastructure to avoid a conflict in utility services underground.

    Light vehicle access
    Light vehicle traffic entering from the north can access the Margaret River town site via Bussell Highway and following detours up Higgins Street and along Townview Terrace. Local traffic will still be able to access businesses and properties north of the Coles Express service station.
    Alternatively, light vehicles can access town via the Perimeter Road and John Archibald Drive.

    Heavy and long vehicle access
    Heavy vehicles, including buses and vehicles towing trailers or caravans, are requested to use the Perimeter Road and enter Margaret River town via John Archibald Drive.

    Access to businesses in front of the closure site
    Visitors to JahRoc Galleries, Swings & Roundabouts Taphouse, Margaret River Bakery, Margaret River Collaborative and Innetown Backpackers are reminded that there is some parking available behind most of these shops on Ned Higgins Lane. Full pedestrian access will be maintained in front of these shops.

    Pedestrians will be able to access Margaret River Happy Times gift shop on foot. Access for guests staying at Margarets Forest Holiday Apartments will be provided.

  • Progress update 26 February

    about 1 month ago
    Top roundabout update

    Works are on schedule at the Bussell Hwy/Wallcliffe Rd/Forrest Rd intersection. Stormwater drainage has been fully installed on the west side of the intersection and is connected to existing drainage in Reuther Park, meaning we are prepared for rainfall. Excavation works on the eastern side of the intersection will begin soon with all drainage works at the top intersection expected to be completed by the end of next week. Footpath construction will commence once the stormwater drainage works are complete.



    Works are on schedule at the Bussell Hwy/Wallcliffe Rd/Forrest Rd intersection. Stormwater drainage has been fully installed on the west side of the intersection and is connected to existing drainage in Reuther Park, meaning we are prepared for rainfall. Excavation works on the eastern side of the intersection will begin soon with all drainage works at the top intersection expected to be completed by the end of next week. Footpath construction will commence once the stormwater drainage works are complete.



  • Progress update 17 February

    about 1 month ago
    South intersection pipes pic

    Wallcliffe Road/Bussell Highway intersection update

    Works are progressing well at the top end of town. Before the new roundabout is built, old stormwater infrastructure under ground is being replaced. Work crews have dug down about 3.5 meters to the centre junction pit, laying eleven, 450mm stormwater pipes. The team is now working west of the intersection on Wallcliffe Road, digging four side entry pits. These are the little openings you see along kerbs designed to collect stormwater from the road surface. Once this is done, they’ll begin making side entry pits to the north and east side of the intersection.

    ...

    Wallcliffe Road/Bussell Highway intersection update

    Works are progressing well at the top end of town. Before the new roundabout is built, old stormwater infrastructure under ground is being replaced. Work crews have dug down about 3.5 meters to the centre junction pit, laying eleven, 450mm stormwater pipes. The team is now working west of the intersection on Wallcliffe Road, digging four side entry pits. These are the little openings you see along kerbs designed to collect stormwater from the road surface. Once this is done, they’ll begin making side entry pits to the north and east side of the intersection.



    Tunbridge Street/Churchill Avenue intersection

    Crews have been potholing to confirm the location of utility services under the ground. This involves careful vacuum excavation to allow visual confirmation of services and other unknown obstructions before starting deep excavation. The location of huge1500mm diameter stormwater pipes to be installed between Tunbridge Street and the rain garden are being moved from the northbound carriageway to the centre of the road. This will require a portion of Bussell Highway to close whilst excavation works take place and pipes are laid. Updated detour map is available here.




  • Driver safety message

    about 2 months ago

    Whilst most drivers are following detours, there have been a number of incidents where people are ignoring red lights, stop bats and even taking risks driving on the wrong side of the road into oncoming traffic to avoid detours. We ask drivers to follow detour signage and the directions of traffic management personnel to avoid a serious incident happening. We appreciate your help in spreading this message.

    Whilst most drivers are following detours, there have been a number of incidents where people are ignoring red lights, stop bats and even taking risks driving on the wrong side of the road into oncoming traffic to avoid detours. We ask drivers to follow detour signage and the directions of traffic management personnel to avoid a serious incident happening. We appreciate your help in spreading this message.

  • Stormwater pipes arrive

    about 2 months ago
    Reinforced concrete pipes

    Check out the size of these pipes! Reinforced concrete pipes have arrived and will be installed underground at the north end of town in the coming months to improve drainage on the Main Street. The 1500mm diameter pipes carry storm water into the bioretention basin (rain garden) which naturally filters water before it infiltrates the river.


    Check out the size of these pipes! Reinforced concrete pipes have arrived and will be installed underground at the north end of town in the coming months to improve drainage on the Main Street. The 1500mm diameter pipes carry storm water into the bioretention basin (rain garden) which naturally filters water before it infiltrates the river.


  • Detour Information (From 3 Feb 2020)

    about 1 month ago
    CLOSED: This discussion has concluded.
    Revised plan 1

    Stage 1 of the Margaret River Main Street Makeover will begin 3 February until 30 May 2020.

    Detours and traffic management will be in place at all times during this period. Please follow the directions of traffic management personnel and follow the directional detour signage at all times. Pedestrian and bike access will be clearly signposed.

    Access to Settler’s Tavern, IGA and other businesses via Tunbridge Street will remain open at all times. If you have any questions, please contact Shire Project Manager, Peter Brown 0481 460 578

    Map above includes detours from 3 Feb - 4 March 2020

    Stage 1 of the Margaret River Main Street Makeover will begin 3 February until 30 May 2020.

    Detours and traffic management will be in place at all times during this period. Please follow the directions of traffic management personnel and follow the directional detour signage at all times. Pedestrian and bike access will be clearly signposed.

    Access to Settler’s Tavern, IGA and other businesses via Tunbridge Street will remain open at all times. If you have any questions, please contact Shire Project Manager, Peter Brown 0481 460 578

    Map above includes detours from 3 Feb - 4 March 2020

    DOWNLOAD additional detour maps for all of Stage 1 ( until end of May)*

    *Subject to change. Whilst detour dates have been planned in advance, they may be updated pending progress of the project.
  • Community information session

    2 months ago
    Jan 2020 info session

    Come along to hear more about the detailed plans for the timing of works and traffic management for February 2020.

    Tuesday 21 January 5.30-6.30pm in Margaret River Council Chambers



    Come along to hear more about the detailed plans for the timing of works and traffic management for February 2020.

    Tuesday 21 January 5.30-6.30pm in Margaret River Council Chambers