Turner Street Jetty
On Wednesday 19 March 2025, the Turner St Jetty was closed off to members of the public based on expert engineering advice to ensure public safety. Our community and visitors alike are understandably frustrated, surprised and saddened by the closure of this important and much-loved asset.
We know there are a lot of unanswered questions, many of which we will only be able to answer in the fullness of time (e.g. when will the jetty be reopened, what would this look like) and we are committed to keeping the community updated along the way.
To resolve the closure as soon as possible, the Shire made the Turner Street Jetty urgent business at the Wednesday 26 March 2025 Ordinary Council Meeting in Augusta. At the Ordinary Council Meeting held on Wednesday 26 March 2025 decided that Council:
1. Notes the intent to concurrently investigate two primary options for the future of the Turner Street Jetty, being renewal of failed components of the existing structure or alternatively, replacement of the existing structure.
2. Notes that in consultation with a dedicated community reference group, the two options of significant renewal or replacement will be explored with the community prior to procurement of the preferred option.
3. Endorses an amendment to the 2024-25 Annual Budget allowing for design and costing of options to renew or replace the Turner Street Jetty, with funding of up to $100,000 being made available for these works from the Asset Renewal Reserve.
Since then, we have investigated the feasibility of several options and formed a Turner Street Jetty Community Reference Group with 20 community participants. These options were recently presented to the group, who showed support for removing the existing jetty structure, and designing and reconstructing a fixed timber decked jetty. This option comes with a price tag of around $660,000 which is a significant investment that will affect other projects that we can deliver.
We will continue to progress with detailed design however before we commit, we will be asking for community feedback to make sure that this choice reflects everyone’s priorities. Thank you to the Community Reference Group for your time, effort and passion so far - it is greatly appreciated.
You can also find out more by reading:
- Community Working Group - Meeting 1 Outcomes
- Extract of the March 26 OCM Minutes
- Asset Investigation Report 2025
- Asset Investigation Report 2023
You can also read the full Frequent Asked Questions we’ve been asked that may help explain how we got to this point, and what you can expect next.